Hydrogen project operational status

How do you define operation status of a hydrogen project

K
Written by Kirsten Tainsh

The operational status is the current status of the hydrogen phase or project.

Hydrogen project statuses include:

  • Announced - agreement, LOI, MoU, Phase 2 -X

  • Pre-development - pre-feasibility, business plan, land acquisition

  • Early-development - feasibility studies, basic engineering studies, pre-FEED activities

  • Development - FEED, funding secured, permitting and regulatory processes in progress

  • Advanced development - post-FEED, FID imminent, EPC awarded, permits received or in final stages

  • Under construction - FID taken, construction commenced

  • Operational - operational

  • Inactive - This applies to projects which have not been formally cancelled but on which we understand work to have been halted. Projects are judged individually but common signs of inactivity that we look for are removal of the project from a developer website or company presentations, no project updates or relevant press releases in >2 years, or any other reason to believe that work on the project is halted.

Viewing Hydrogen Projects by Operational Status

You can view hydrogen projects by operational status within the Assets workflow.

Use the Settings icon in the top-left corner of the chart and select Colour by Operational Status.

Alternatively, you can view the operational status for each project in the Hydrogen Project located at the bottom of the Assets workflow.

Filtering Projects by Development Status

To filter projects by development status, navigate to:

Assets > Hydrogen Projects > Development