Hydrogen project operational status
Hydrogen project operational status

How do you define operation status of a hydrogen project

K
Written by Kirsten Tainsh
Updated over a week ago

The operational status is the current status of the hydrogen phase or project.

Hydrogen project statuses include:

  • Announced - agreement, LOI, MoU, Phase 2 -X

  • Pre-development - pre-feasibility, business plan, land acquisition

  • Early-development - feasibility studies, basic engineering studies, pre-FEED

  • Development - FEED, funding secured, permitting and regulatory processes ongoing

  • Advanced development - post-FEED, FID imminent, EPC awarded, permits received or in final stages

  • Under construction - FID taken, construction started

  • Operational - operational

You can view hydrogen projects by operational status under the 'Assets' workflow. Use the settings cog on the top left of the chart to colour by operational status:

Or you can view the operational status in the low carbon hydrogen project list at the bottom of the 'Assets' workflow:

You can filter for projects by development status within the Assets > Hydrogen project > Development menu.